As of the 18th of February 2018 the second phase of the shed project has made rapid progress.
In the three weeks since the last of the foundation pads were poured, all 12 of the uprights have been installed along with two of the roof girders and the outer roof wooden beams.
Two sections of the intermediate roof wooden beams have been installed too.
The work is being carried out as a joint effort between the Engineering Services and Infrastructure teams, along side their normal tasks around the railway. Thanks is given to them and here’s an appeal to everyone to get involved with the fund raising for the cladding & shed doors.
- Infrastructure team member David Millard stands by the first shed upright to be installed on 28 Jan 2018. Photo Credit Kevin Proctor
- With all of the uprights installed on 11 Feb 2018, he view along the siding looks a touch different. Photo Credit: Graham Peacock
- A view from the top of the 4th low side upright, during wooden roof beam installation. Photo Credit Graham Peacock
- With all of the uprights in place along with two of the roof girders; the infrastructure team prepare to install one of the outer roof beams on 18 Feb 2018. Photo Credit: Tim Casentieri
More details about the project can be found at http://nlr.org.uk/blog/appeal-loco-shed-project/, where you can find links to make a donation to the project. Fundraising is just over half way & has enabled the foundations and basic framework to be purchased & installed.